MARTA Planning staff has completed the review of community feedback and technical analysis and have finalized a recommended locally preferred alternative (LPA) for the Clifton Corridor. The LPA is the alternative that, based on technical analysis and stakeholder input, would most effectively address the needs of the corridor and goals and objectives of the project.
The recommended LPA includes 8.8 miles of new light rail transit (LRT) service connecting the Lindbergh MARTA Station to the Emory/Clifton Corridor and beyond to the Avondale MARTA Station. The recommendation for the locally preferred alternative includes several tunnels and one of those tunnels extends from an area west of Lenox Road to an area just west of Briarcliff Road.
MARTA Planning staff will present the LPA recommendation to the MARTA Planning and External Relations Committee on March 26 at 10:00 a.m. and to the MARTA Board on April 9 at 1:30 p.m. There will be a public comment period prior to the Board meeting only. Both meetings will be held at:
MARTA Headquarters, 6th Floor Board Room, 2424 Piedmont Road, Atlanta, GA 30324.
Upon MARTA Board approval, the agency will present the LPA to the Atlanta Regional Commission for adoption and incorporation into the long-range transportation plan. Afterwards, the LPA will be advanced through the next step in the federal project development process which is the completion of a Draft Environmental Impact Statement (DEIS). This study will go into much more detailed level of analysis as compared to the Alternatives Analysis (AA).
The Lindbergh LaVista Corridor Coalition (LLCC) in conjunction with the Morningside Lenox Park Association (MLPA), and the Woodland Hills Neighborhood Association (WHNA) hired Heather Alhadeff, Senior Transportation Planner with Perkins + Will, to assist us in disseminating information to the public, collecting this input, and preparing a formal document for inclusion in the AA. This document which includes a summary along with all results and comments from our surveys is included. Inclusion in the report best positions our communities in the federal process moving forward.
The Fact Sheet recently released by MARTA has concerned some in our community as it did not mention tunneling of the project or a Morningside station. The purpose of a Fact Sheet is to comment ONLY on the alignment and technology preferences for the project. It is not intended to address the project in great detail. For this type of information one will have to review the study document. I have reached out to Jason Morgan, Project Manager, for the CCTI requesting additional summary details regarding the second segment (from Cheshire Bridge to Briarcliff) as I have received emails with questions. I share below his comments in an effort to address some of these matters and provide clarity to the public.
Email correspondence from Jason Morgan, Project Manager MARTA:
The fact sheet that has been distributed does not preclude the tunnel. The tunnel is part of the proposal. In fact, there are three tunnels that are included with the proposal. The second and third tunnels are further east along the alignment. The fact sheet is not intended to go into the details regarding where every tunnel or elevated structure is located. We have other materials which illustrate the specific station concepts and tunnel proposals. We have done our best to balance the comments from members of the community throughout the entire project corridor with our best technical analysis. The LLCC report has provided valuable insight into the perspective of residents in this section of the corridor, but the project team must consider cost and potential construction issues as well.
With that said:
A bored light rail tunnel is proposed to run parallel to and beneath the northside of CSX right-of-way.
The tunnel depth will be a minimum of 55 feet. The specifics of the tunnel design will be determined during the Environmental Impact Study which has been targeted to begin later this year.
Specific impacts and compensation are quantified during the Environmental Impact Study and in accordance with guidelines identified within the National Environmental Policy Act.Keep in mind, this corridor is 8.8 miles long and most of the potential impacts or displacements we can estimate at this stage are in areas where the alignment is above ground.
While a station at Lenox Road was requested to be examined, ultimately many residents expressed trepidation about having a station close to their homes. In addition, there was a significant additional estimated cost associated with building a subway station at this location. The suggestion from attendees at the October 25 meeting as well via many comments was to add a walking trail that would connect Lenox Road to the station at Cheshire Bridge. This trail could be integrated with the South Fork of Peachtree Creek trail as well as others.
Revised station concepts and alignment concepts are currently being updated to the project website (www.itsmarta.com/clifton-corr.aspx). MARTA hopes to have everything activated by later this week.
Sincerely,
Jane Rawlings, Transportation Coordinator
Lindbergh LaVista Corridor Coalition, Inc.